Assessing and Tracking Team Performance – Part 7: “Abandon All Hope,…”

“…ye who enter here.” So reads the inscription to the Gates of Hell in Dante Alighieri’s epic poem, “Divine Comedy.” Who among us hasn’t felt on occasion that stepping across the threshold to our place of employment is like passing through the gates of Dante’s Inferno? But as the poets have told us, the way to peace is to find the path through our troubles. In this article, we’ll look into just how deeply project system dynamics can adversely affect progress and even whether or not the project is successful.

But I do want to arm the reader with a couple of rays of hope. The concluding article in this series will focus on how this system model1 can be used to good effect, how it can be used to identify problems before they grow out of control. Therein lies the path to peace. Before we get there, we need to understand several more influential feedback loops.

As the Delay to Completion becomes critical, management begins to panic. Not wanting to push the deadline out they work to influence the other three options focused on modifying the behavior of the delivery team. The end result is a team that is caught in the Work Faster, Work More, and Add People loops along with all the other associated downstream loops. The effect is compounded by the emergence of other feedback loops if teams are placed in this position for an extended period of time.

Over time, the shortcuts, hacks, and quick fixes put in place to keep the pace of progress as high as possible settle in as technical debt. They work – for now – so they don’t surface as errors for quality assurance to discover. Down the road, however, solutions hastily put in place as stop-gaps fail when later solutions require existing solutions to be more robust then they are. For example, a software method that doesn’t take advantage of multi-threading may break when a later solution needs that method to scale beyond it’s single thread capacity. The shortcut is now a defect.

Figure 1 (click to enlarge)

If the technical debt remains in place for an extended period of time, it may be covered by several release layers. When it does flip to defect status due to some later stress, it can be much more time consuming and expensive to uncover. The original developer of the code may not be available or even if she is, it could take her quite a bit of time to become reacquainted with the code. This can be thought of as a form of dark debt and is reflected in the Errors Build Errors Loop (Figure 1, J).

As the teams struggle to keep up the pace of progress and reduce the Delay to Completion, work streams start to become out of sequence. One team has an easier time at crafting their solution while another, to which they are dependent on the output, hits a significant snag and is delayed several weeks. In order to stay busy, the first team starts work on something else while the second team finishes their work. When the second team delivers, the first team is not prepared to immediately shift back to their original work stream and so their deliverable is delayed even further. Meanwhile, a third team, that was dependent on the first team’s deliverable has now been delayed by the cumulative delay of the first two teams. Teams and individuals begin to take shortcuts as delivery of interim work products become out of sync with each other. The diminished focus and desynchronization of work streams leads to an increase in the Error Fraction, which in turn leads to a further Delay to Completion. This is the Haste Makes Out-of-Sequence Work Loop (Figure 1, K).

Figure 2 (click to enlarge)

As the effects of the Haste Makes Out-of-Sequence Work Loop build,  team begin switching back-and-forth between work streams depending on who is making the most noise for the completion of any particular deliverable. This is the Thrash and Churn Loop (Figure 2, L). Switching from stream to stream or, in worst cases, task to task, places a tremendous burden on development teams and can do more to slow progress than almost anything else I’ve encountered in team management. Not covered in this model is the type of churn that occurs when parts of the project undergo redesign after work has begun on the existing design. Long term projects are particularly susceptible to adverse impacts from redesign as the changes are often farther reaching. The drivers behind a redesign can range from trivial (a new CTO has a personal dislike for a platform vendor) to critical (a security flaw uncovered in a core technical component.)

If all the loops described to this point in the article series are allowed to run uncorrected the system is likely to crash as the project becomes one massive firefighting effort. A key indicator for when this is happening is employee morale.

Figure 3 (click to enlarge)

The increased Fatigue, the growing burden of Work/Rework to Do, the unsatisfying Task Switching between work assignments all combine to causes a decrease in team Morale. This is the Hopelessness Loop (Figure 3, M). Teams are left with a powerless feeling of being caught on a never ending treadmill. And so, stepping across the threshold to the office is like passing through the gates of Dante’s Inferno.

The ripple effect from a decrease in Morale leads to a decrease in the Workforce as employees leave the organization in search of less stressful, more satisfying work. This is the Turnover Loop (Figure 3, N). The remaining demoralized employees are even less productive and unhappy employees make more mistakes, thus increasing the Error Fraction in the system. The downstream result is that the Delay to Completion increases yet again.

If corrective action isn’t taken the law of diminishing returns becomes evident and the system collapses. The cost overruns become prohibitive and the project is cancelled. Worst case, the organization runs out of resources (money, time, or both) and goes out of business. Those are bad things. In the concluding article to this series, we look at how this model can be used to read the current state of a project’s system dynamics and explore some ways we can intervene such that the system doesn’t run out of control.

Previous article in the series: Assessing and Tracking Team Performance – Part 6: It Lives! But it’s Out of Control!